The literals for the duration of roadworks are currently defined like this:
Short Term < 1 month
Medium Term 1 month up to 6 month
Long term > 6 months
Are these definitions still useful like this? Expecially for short term roadworks, our expectation is something like <= 24 hours (think about C-ITS solutions), mid term for example 24 hours up to 3 calendar days.
Proposal is to change the limits or to introduce more stages.
I would prefer to get this clarified for the 3.0 version.
Found Version
{"changeLogs":[{"date":1528364281722,"componentOLD":"- Select a value -","component":"UML General","categoryOLD":"- Select a value -","category":"Bug report","priorityOLD":"- None -","priority":"Normal","assignedOLD":"","assigned":"iancornwell (42)","statusOLD":"- None -","status":"Fixed"},{"date":1537267673174}]}
#1
Fixed in comment resolution for Enquiry, in revision 794